Setterwalls has assisted Arise AB in the permit process for Finnåberget
Setterwalls‘ team, consisting of Tove Andersson and Jonathan Andersson, has successfully assisted Arise AB in the permit process for the wind power project Finnåberget in Ragunda and Sollefteå municipalities.
The Permitting authority at the County Administrative Board of Västernorrland County has granted an environmental permit for 26 WTGs with a total height of 240 meters each on 28 April 2021. The permit decision can be appealed to the Land and Environment Court.