Uppdrag | 26 Jun 2023
Environmental permit to restart the Dannemora mine
Setterwalls has successfully represented Dannemora Iron AB in the permit process to restart the Dannemora mine.
The Land and Environment Court in Nacka has 22 June 2023 granted Dannemora Iron AB, part of the GRANGEX group, environmental permit to restart the Dannemora mine. The permit application was submitted to the court in June 2022 and permit has now been granted in accordance with the company´s application.
GRANGEX Dannemora intends to be the first producer of high-quality iron ore concentrate in the EU and with the smallest carbon footprint.
Contact:
Practice areas: